What is this Project?

This project increases system capacity to deliver high-quality drinking water from the Clackamas River to the communities of Lake Oswego and Tigard. Together these two communities can secure long-term access to clean, safe water for less than it would cost them to do it alone. Learn more...

Project News

Friday - September 12, 2014

Have you seen our updates on Facebook?

How better to keep up to date on the project in your neighborhood than having the information instantly available through your Facebook feed? We are posting updates about the project to the Lake Oswego Tigard Water Partnership Facebook page, so come “like” our community page and stay informed!

Thursday - September 11, 2014

Waluga Reservoir 2 (WR2) Construction Update

Placing the wall form for the first wall pour

WR2 foundation footing pours complete

Crews completed the last foundation footing concrete pour and have now begun construction of the reservoir walls.

Exploratory digging at Parkhill Drive complete

Crews completed exploratory digging to locate underground utilities which ensured against conflicts with existing utilities around Parkhill Drive.

Crushing rock to re-use as fill

In a sustainable effort to reuse natural resources from the WR2 site, crews will be crushing rock later this week and early next week. The crushed rock will then be used as fill material on site. [This was slightly delayed due to an equipment breakdown.]

Read More

Friday - September 5, 2014

Gladstone Pipeline and River Intake Construction Update

Divers removing remaining sand bags as well as some piling from the river.

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • River Intake Pump Station (RIPS) on the Clackamas River
  • Gladstone pipeline work progressing north on Bellevue Avenue
  • Horizontal directional drilling under the Willamette River in Meldrum Bar Park

For the most up to date information on construction and road closures, please visit work underway or contact us.

Read More

Thursday - August 28, 2014

Bonita Pump Station Construction Update

Rexius Sustainable Solutions applying organic compost at the site.

Invasive species have been removed from the vegetated corridor around the protected wetland. Last week, organic compost was spread throughout the corridor in preparation for the seeding of native grasses. This week, the corridor was seeded with a native erosion control grass mix that is quick to establish, low-growing and has good root masses for reduced erosion of soil. The native grass mix includes ‘Meadow Barley’ and ‘Native Red Fescue’ (among other native grasses) and has excellent versatility and tolerance for various weather. The native grasses may start to emerge by early next week.

Read More

Friday - August 22, 2014

B Avenue Stormwater System Construction Update

This week, construction began for the much needed new stormwater system upgrade on B Avenue at State Street. During construction, B Ave. is closed to traffic between State and 1st St.

Change in work hours

Per ODOT requirements, B Avenue will be closed 24 hours a day, between OR43 and 1st St, Monday to Friday, during storm line construction. This closure will last through early September.

Support of the business community is a high priority for the project. To maximize productivity and complete construction of the stormwater system upgrade in advance of the 2014 holiday season, construction hours are being modified on B Ave. Once crews work through the first block of B Ave., west of 1st Street, work hours will change (from 9 a.m. to 4 p.m.) to 7 a.m. to 6 p.m., Monday to Friday.

Read More