Previous Entries

Older entries are listed below. You may also browse articles by month.

 
Monday - January 27, 2014

Water Treatment Plant Construction Update

All 250 auger cast piles in the clearwell and 78 piles in the ballasted flocculation are now complete! The smaller drill rig is now being demobilized and will be removed from site next week. The large drill rig will remain on site to drill piles for other foundations.

Demolition of the two existing lagoons on the northeast of the site is underway. A hydraulic hammer will break up the remaining base of the lime building next week. Starting Monday, the stockpiled concrete will be crushed on-site for later reuse. Crushing will occur after 8 a.m. toward the middle of the site and with the fan facing inward to reduce noise. Crushing the material for later reuse on site reduces truck traffic in the neighborhood by over 1,300 one way trips.

Read More

Friday - January 17, 2014

Pipeline Construction Update:

East Waluga Park, Lanewood St. and Iron Mtn. Blvd.

Construction of the 24” pipeline in the upper portion of Waluga Park near Parkhill Street is almost complete!

Starting the week of January 20, crews will begin installing pipe in the East Waluga Park parking lot and progressing towards Quarry Road. This section of the pipeline is expected to be complete by the end of February 2014. Park trails and areas disturbed during construction of the pipe will be restored with gravel or reseeded and planted later in spring.

Generally, over the next month work hours will be 7:00 a.m. to 5:00 p.m. Monday to Friday. Once construction is complete in the Park, crews will move east of Boones Ferry Road, installing pipe along Lanewood Street and Douglas Circle. Construction work along Douglas Way, Lake Grove Elementary School and Boones Ferry Way will occur in summer.

Click "more" below to learn about other current and upcoming pipeline work in Lake Oswego including:

  • The temporary road closure on Lanewood Street
  • Tree trimming (Lanewood Street to Chandler Road)
  • Sewer line relocation on Iron Mountain Boulevard

Read More

Wednesday - January 15, 2014

River Intake Construction Update

The river intake pump station walls are taking shape! The first 30 feet of walls are now formed with concrete in the cofferdam.

This week, work will begin on forming the structural interior pump walls. Starting on Thursday, a large concrete pour will occur around the interior forms. This should take about two days to complete.

Read More

Tuesday - January 7, 2014

Local Pipe Manufacturer at work for the Partnership

A local company in North Portland is preparing the new pipe that will carry water from the Clackamas River to  Lake Oswego and Tigard.  Learn about the process of building this pipe and the features that make it strong and stable for a long life serving our customers.

Friday - January 3, 2014

Water Treatment Plant Construction Update

Drilling and installation of the auger cast piles continues in the clearwell and finished water pump station. Early next week, a second drill rig will arrive and begin installing auger cast piles for the base of the ballasted flocculation building.

In mid January, the contractor will begin demolishing the lime building and preparing two of the existing lagoons on the northeast of the site for demolition. This will involve breaking up the concrete, then stockpiling and crushing it on-site for later reuse. Concrete crushing is scheduled to occur in early February.

During the demolition work, there is the potential for increased noise during work hours, depending on neighbor’s locations or personal sensitivities.

Generally over the next month, work hours will be Monday to Friday from 7:00 a.m. to 5:00 p.m. and Saturdays, from 9:00 a.m. to 5:00 p.m.

The table below describes what activities are happening on-site over the next few weeks, the purpose and estimated duration of work.

Read More

Thursday - January 2, 2014

River Intake Construction Update

Updated January 2, 2014

Work is continuing on forming the pump station walls at the river intake construction site in Gladstone, with the first 15 feet of walls now formed with concrete.

The second level wall forms are now being installed above the first level concrete walls. A large concrete pour is scheduled to occur around these forms on January 6, which should take about one day to complete. After the pour, the concrete will set in place for a few days before the wall forms are removed from the second level and reinstalled above the newly poured concrete. Reinforced bar will also be added to support the walls.

During the concrete pour, neighbors can expect some noise and an increase in truck traffic as 12-15 concrete trucks arrive at the site. Generally, during the next three weeks, work hours will be 7:00 a.m. to 6:00 p.m. Monday through Saturday. No work will occur on New Year’s Day.

We wish everyone a safe and happy holiday season.