Friday - May 30, 2014

Gladstone Pipeline and River Intake Construction Update

This update includes work in the following areas of Gladstone. Scroll down for specific information on each location:

  • River intake pump station (RIPS) on the Clackamas RiverPipelines east of McLoughlin Blvd. (W. Clackamas Blvd., Bellevue Ave. and W. Exeter St.)
  • Pipelines in Meldrum Bar Park (horizontal directional drilling under the river)
  • Micro-tunneled pipeline under McLoughlin Blvd. and River Road

Read More

Friday - May 30, 2014

West Linn Pipeline Construction Notice: Horizontal Directional Drilling site (end of Mapleton Dr.)

Starting next week, the contractor will begin preconstruction activity at the horizontal directional drilling (HDD) staging area at the end of Mapleton Drive, just north of Mary S. Young Park. This will include mobilizing equipment, placing rock in preparation for the arrival of drilling equipment, installing erosion control and security fencing and placing sound barriers.

Read More

Friday - May 30, 2014

DELAYED: Traffic Alert: Night work on Carman Drive June 3 - 16

This work has been delayed. Please see the delay notice here.

Starting Tuesday, June 3, Waluga Reservoir construction crews will be installing 300 feet of storm drain pipe and manholes, at night (7:00 p.m. to 5:00 a.m.) in Carman Drive. Work is expected to continue through June 16, Monday through Friday, extending along and slightly beyond the Partnership’s parcel at 4800 Carman Drive.

Read More

Thursday - May 29, 2014

Tigard city councilors approve water partnership funding for Gladstone construction

In the news...

Tigard city councilors unanimously approved an agreement with two other cities to help fund street construction and water infrastructure in Gladstone.

The agreement with Lake Oswego and Gladstone draws on funds accounted for in Tigard's $70 million water partnership budget for 2014-15, according to city documents.

Open link to external content

Wednesday - May 28, 2014

Traffic Alert: Upper Dr./Iron Mtn. Blvd./Lakeview Blvd. Traffic Circle

EXPECT TEMPORARY DELAYS

Starting tomorrow, crews will be working within the traffic circle located at the intersection of Upper Drive/Lakeview Blvd. and Iron Mountain Blvd. Flaggers will guide traffic through the traffic circle over the next two weeks while crews work through the circle and move east onto Iron Mtn. Blvd. Expect temporary delays during this work.

For residents living in the Summit Drive and Village on the Lake area, the best thing to do is avoid the traffic circle and Iron Mountain Blvd., and enter/exit your neighborhood at Summit/Lakeview Blvd. to Bryant Rd., to access points east, north and south.

Upper Drive, between Twin Fir and Iron Mtn remains closed until trench paving is complete.

Thank you for your patience during this work.

For the most up to date information on construction and road closures, please visit the work underway map, call the hotline at 503-697-6502 or contact us.

Follow us @LOTWater for regular traffic alerts.

Friday - May 23, 2014

Waluga Reservoir 2 Construction Update: Lake Oswego

This update includes the following topics. Please scroll down for specific information on each topic:

  • Waluga Meet the Contractor Meeting
  • Reservoir site work
  • Work in Carman Drive
  • Noisy Activity! Rock chipping

For the most up to date information on construction and road closures, please visit work underway or contact us.

Read More

Friday - May 23, 2014

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • Upper Drive
  • Iron Mountain Boulevard
  • Downtown Lake Oswego

For the most up to date information on construction and road closures, please visit work underway or contact us.

Read More

Thursday - May 22, 2014

Water Treatment Plant Construction Update

This week, the final wall was poured for the gravity thickener building on the northeast of the site. Crews also began to excavate and install shoring for a new 54” pipe to connect the clearwell and filters. An additional office trailer was also delivered to the site and set up near the existing office complex.

Walls are almost complete in the ballasted flocculation and continue to be poured for the solids storage tank and mechanical dewatering structures. Next week, auger cast pile drilling will resume on the center of the site, to support the new 54” pipe. Refer to the current site plan for locations of each structure.

Over the next few weeks, the clearwell and ballasted flocculation roof slabs will be poured in a checkerboard pattern. The first pour for the clearwell and ballasted flocculation is scheduled for late next week. Waterblasting or sandblasting of the edges of the newly poured slabs will occur within one or two days of a roof pour. Neighbors close to the site on Mapleton Drive and Kenthorpe Way may experience intermittent noise during the sandblasting. Truck traffic will continue during concrete pouring for new structures.

Over the last two Saturdays, Clackamas Fire District #1, Tualatin Valley Fire & Rescue and the Lake Oswego Fire Department have been conducting training (link connects to external site) at the construction site with the contractor, Slayden. The final day of training will occur this Saturday, May 24. There may be some intermittent noise from back-up alarms when the rigs arrive to the site, but this will be minimized.

Read More

Wednesday - May 21, 2014

West Linn Pipeline Construction Update: Mapleton Drive and Willamette River Crossing

Meet the Contractor Meeting – June 3

From June 2, the contractor will begin preconstruction activity at the horizontal directional drilling (HDD) staging area at the end of Mapleton Drive, just north of Mary S. Young Park. This will include mobilizing equipment, placing rock in preparation for the arrival of drilling equipment, installing security fencing and placing sound barriers.

Drilling work is expected to begin at the HDD site from June 18, including installing a pipe casing prior to drilling the actual tunnel. During this work, it will be very noisy for approximately ½ hour periods between 9 a.m. and mid-afternoon. Following each ½ hour period, there will be a couple of hours of welding, which is not as noisy. Immediate neighbors may also experience some vibration during the casing installation. This work will take about 2 weeks to complete. Work hours are 7 a.m. - 7 p.m. Monday to Friday, and Saturdays from 9 a.m. - 5 p.m.

Read More

Tuesday - May 20, 2014

Iron Mt. Blvd. closure

2014-05/ironmtdetour.jpgStarting Wednesday, May 21, Iron Mtn. Blvd., between the westerly leg of Pine Valley Rd. and Summit Drive, will be closed to through traffic between 7:00 a.m. and 6:00 p.m., M-F. 

The closure is expected to remain in place through mid-July, 2014.  Traffic to and from the Oswego Lake Country Club and Fairway Road will be guided by flaggers. 

Please use the alternate east/west route (see map to right) through Lake Oswego during this time.

Thursday - May 15, 2014

Gladstone Pipeline and River Intake Construction Update

Construction updates will now include all work taking place in Gladstone for the project – from the River Intake Pump Station on W. Clackamas Blvd., to the Horizontal Directional Drilling (HDD) staging area in Meldrum Bar Park. Scroll down for specific information on each location:

  • River Intake Pump Station
  • Meet the Contractor Meeting
  • W. Clackamas Blvd., Bellevue Ave. and W. Exeter St.
  • Meldrum Bar Park

Read More

Friday - May 9, 2014

Pipeline Construction Update: Lake Oswego

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • Lanewood Road/Douglas Circle
  • Twin Fir Road
  • Upper Drive
  • Iron Mountain Boulevard
  • Downtown Lake Oswego

For the most up to date information on construction and road closures, please visit work underway, call the hotline on 503-697-6502 or contact us.

Read More

Thursday - May 8, 2014

Partnership wins AWWA Excellence in Communications Award

In the news...

The Lake Oswego Tigard Water Partnership was one of eight utilities from Idaho, Washington and Oregon to win an Excellence in Communications award from the Pacific Northwest Section of the American Water Works Association (PNWS-AWWA) this week.

Read More

Wednesday - May 7, 2014

Exploratory Digging Work - Hwy 43

Between Laurel St., Lake Oswego and Mapleton Drive, West Linn

Beginning late next week and continuing through June, crews from the Water Partnership project will be digging small holes in the roadway on Highway 43 locating underground utilities and pipes, to ensure the pipeline route has no conflicts with existing utilities.

Read More

Monday - May 5, 2014

Join the LO and Tigard Mayors Celebrating Drinking Water Week

Learn more about events planned this week and partiicapte in the drinking water trivia contest.

Friday - May 2, 2014

National Drinking Water Week May 4th-10th

When you turn on your tap and clean, safe water comes out...

Do you ever stop to think about how it gets there and where it goes when you're finished with it? The Lake Oswego Tigard Water Partnership and the cities of Lake Oswego and Tigard are celebrating Drinking Water Week from May 5-9, 2014. We invite you to celebrate this week by taking time to learn more about your water and how you can protect and conserve it.

Here in Oregon we often take our drinking water for granted, but it's a finite resource.  Significant costs and energy are required to treat our drinking water to be clean and safe, deliver it to our taps, and manage the wastewater that goes down the drain. Spend a moment this week thinking about the essential role that water plays in your daily life.

Our water in Lake Oswego and Tigard is of the highest quality - let’s celebrate it!

Read More

Thursday - May 1, 2014

Waluga Reservoir 2 - Meet the Contractor Meeting and Construction Update

We hope that you can join us to meet representatives from Ward-Henshaw Construction and learn more about the Waluga Reservoir 2 construction, which will begin in mid May.

The Meet the Contractor meeting will be held on Wednesday, May 14 from 7 p.m. to
8:30 p.m. at the West End Building, Santiam Room, 4101 Kruse Way, Lake Oswego. We will have information about the project, the work schedule, and what to expect in the neighborhood.

Starting the week of May 12, expect to see some preconstruction activity on site at 4800 Carman Drive, including mobilizing equipment, removing tree stumps, and installing erosion control fencing. Work hours will be 7 a.m. to 6 p.m. Monday to Friday.

For more information, contact us or call the hotline at 503-697-6502.