Friday - June 27, 2014

Crews begin digging tunnel under Willamette River

By Michael Bamesberger, The Oregonian

In the news...

Ever wonder what it takes to install a water pipeline under the Willamette River?

A powerful pressured hammer, a steerable underground drill and months of work, at the very least.

Next week, construction crews will begin drilling under the riverbed as part of a massive update to Lake Oswego and Tigard's water systems.

Open link to external content

Thursday - June 26, 2014

West Linn Pipeline Construction Update: Horizontal Directional Drilling site (end of Mapleton Dr.)

Pipe casing installation starting tomorrow – noisy activity

The pipe casing work is expected to begin tomorrow at the HDD site, just north of Mary S. Young Park. The 60-inch steel casing will be installed using a large pressurized hammer, through softer soils to reach solid ground (about 200 feet). The casing provides protection for the pipe to be tunneled under the river.

During the pipe casing hammering (known as pipe ramming), it will be very noisy for approximately 1 - 3 hour periods during work hours, depending on conditions. Work hours are 7 a.m. - 7 p.m. Monday to Friday, and Saturdays from 9 a.m. - 5 p.m. Depending on locations and terrain, neighbors may hear noise during the casing hammering. The contractor will aim to start the noisiest work after 9am through mid-afternoon. Following each hammering period, there will be a few hours of cleaning and welding, which is not as noisy. The hammering schedule will vary depending on progress and conditions – it could take place a few times a day, or occur every 1-2 days. This work is expected to take about two weeks to complete, depending on ground conditions. Immediate neighbors to the site may experience some vibration during the casing installation. No work will take place on the Fourth of July weekend.

Read more for information about:

  • Meldrum Bar Park – casing installation continues
  • Neighborhood Construction Meetings at the Burgerville in West Linn

Read More

Thursday - June 26, 2014

Gladstone Pipeline and River Intake Construction Update

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • River intake pump station (RIPS) on the Clackamas River
  • Pipelines east of McLoughlin Blvd. (W. Clackamas Blvd., Bellevue Ave. and W. Exeter St.)
  • Horizontal directional drilling under the river in Meldrum Bar Park
  • Gladstone tree removal completed at boat ramp parking area in Meldrum Bar Park

For the most up to date information on construction and traffic impacts, please visit work underway or contact us.

Read More

Monday - June 23, 2014

Strong and Safe Water Reservoirs

In the news...

Keeping drinking water safe is vital to the health and economy of our communities and reservoirs play an important role. Recent earthquakes in Mexico, Chile and Japan have given engineers a better understanding of the effects of catastrophic events on key facilities like power and water.

Read More

Friday - June 20, 2014

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • Safety reminder: pedestrians and cyclists
  • Quarry Road and Douglas Way – Detour!
  • Iron Mountain Blvd. update
  • State Street and B Ave intersection- June 25 night work
  • McVey Ave. - Downtown Lake Oswego – utility locates through July
  • "Meet the Contractor" meeting for Laurel/Erickson/HWY 43 (between Laurel and Marylhurst) scheduled for July 16.
  • Thank you residents for your understanding during construction!

For the most up to date information on construction and road closures, please contact us.

Read More

Friday - June 20, 2014

Water Treatment Plant Construction Update

Concrete work continues to progress for new structures across the site, including the ballasted flocculation, clearwell, mechanical dewatering building and solids storage tank. Refer to the current site plan for locations of each structure. This week, the first leak test for the new gravity thickener building began and crews encased the 54” pipe connecting the new clearwell and filters in concrete.

Read More

Thursday - June 19, 2014

Waluga Reservoir 2 Construction Update: Lake Oswego

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • NW Natural Gas work in Carman Dr.: 6/20 to 6/25, M-F, 8 a.m. – 3 p.m.
  • Other Carman Dr. roadwork
  • Reservoir site work: rock crushing, rock placement, access road work
  • Quarry Road closure

For the most up to date information on construction and traffic impacts, please visit work underway or contact us.

Read More

Wednesday - June 18, 2014

West Linn Pipeline Construction Update: Horizontal Directional Drilling site (end of Mapleton Dr.)

Mobilization continues at the HDD site, just north of Mary S. Young Park

Crews are excavating, placing rock, fencing and building a work area at the HDD site, which will continue over the next week. A sound barrier will also be installed, prior to the pipe casing installation. Neighbors may notice an increase in truck traffic on Mapleton Drive as equipment arrives to the site and noise from new equipment operating at the site.

Read More

Friday - June 13, 2014

Carman Drive and Waluga Reservoir 2 (WR2) Construction Update

This update includes the following topics. Please scroll down for specific information on each:

  • Gas service line broken 6/11/14
  • Road work on Carman Drive
  • Reservoir site work - rock crushing

For the most up to date information on construction and traffic impacts, please visit work underway, call the hotline on 503-697-6502 or contact us.

Read More

Thursday - June 12, 2014

West Linn Pipeline Construction Update: Horizontal Directional Drilling site (end of Mapleton Dr.)

Mobilization at the HDD site, just north of Mary S. Young Park

This week, crews started surveying and clearing the HDD site at the end of Mapleton Drive, mobilizing equipment and installing fencing. This will continue over the next week, including placing rock and sound barriers at the site. Neighbors may notice an increase in truck traffic on Mapleton Drive as equipment arrives to the site.
Early next week, the contractor will begin excavating and building a work area at the HDD site. Once the work area is complete, the pipe casing will be installed.

Pipe casing installation – noisy activity

Beginning from Wednesday, June 18, a 60 inch steel pipe casing will be installed at the HDD site, prior to drilling the tunnel. The casing will be installed using a large pressurized hammer, through softer soils to reach solid ground. The casing provides protection for the pipe to be tunneled under the river.

Read More

Thursday - June 12, 2014

Gladstone Pipeline & River Intake Construction Update

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • River intake pump station (RIPS) on the Clackamas River
  • Pipelines east of McLoughlin Blvd. (W. Clackamas Blvd., Bellevue Ave. and W. Exeter St.)
  • Pipelines in Meldrum Bar Park (horizontal directional drilling under the river)
  • Micro-tunneled pipeline under McLoughlin Blvd. and River Road
  • City of Gladstone to close Meldrum Bar boat ramp and parking area on June 25

Read More

Thursday - June 12, 2014

Bonita Pump Station Construction Update

Groundbreaking event assisted by Learning Tree preschoolers

As elected officials mentioned during the groundbreaking, the new water system is all about future generations. That’s why the Bonita Road Learning Tree “Bumblebees” were on hand to help celebrate the start of construction at the Milton Court site, in Tigard. Check out the fun!

Read More

Wednesday - June 11, 2014

Pre-schoolers help Tigard officials celebrate Bonita Pump Station Construction

Sixteen Bonita Road Learning Tree students from the “Bumblebee” class helped some Tigard elected officials celebrate the groundbreaking for the Bonita Pump Station (BPS) on Thursday, June 5. Sixteen small hard hats and child-sized “golden” shovels mirrored those used by the elected officials, Tigard Mayor John Cook, Tigard Councilor Jason Snider and Lake Oswego Mayor Kent Studebaker.

Click here to watch a video of the groundbreaking event!

Read More

Friday - June 6, 2014

Waluga Reservoir 2 Construction Update: Lake Oswego

This update includes the following topics. Read more for specific information on each:

  • Road work in Carman Drive starts next week
  • Reservoir site work
  • Noisy Activity! Rock chipping

For the most up to date information on construction and traffic impacts, please visit the work underway map, call the hotline at 503-697-6502 or contact us.

Read More

Friday - June 6, 2014

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas. Scroll down for specific information on each location:

  • Summit Drive and Village on the Lake - water shutoff alert
  • Quarry Road and Douglas Way
  • Upper Drive
  • Iron Mountain Boulevard
  • State Street

For the most up to date information on construction and road closures, please visit work underway or contact us.

Read More

Friday - June 6, 2014

Water Treatment Plant Construction Update

This week, the auger cast piles and slabs were completed for the 54” pipe to connect the clearwell and filters and concrete was poured for the clearwell roof slabs. Crews also continued pouring walls for the solids storage tank and preparing wall forms for the mechanical dewatering building.

Next week, crews will install man holes and backfill for the 48” overflow pipe near the chemical building and excavate for other miscellaneous drainage pipes, near the ballasted flocculation. Work will also begin on leak testing the gravity thickener building. Refer to the current site plan for locations of each structure.

Read More

Thursday - June 5, 2014

HWY 43 - Exploratory digging and NW Natural gas relocation

Two crews will be working on Highway 43 in Lake Oswego and one crew in West Linn over, approximately, the next two weeks.

Northwest Natural Gas will be relocating a gas main on Hwy 43 between Glenmorrie Terrace and Cherry Lane in Lake Oswego.

LO Tigard Partnership crews are continuing to dig small holes in the roadway on Highway 43, progressing from Laurel St in Lake Oswego and working south to Mapleton Drive in West Linn. This work is to locate underground utilities and pipes, to ensure the pipeline route has no conflicts with existing utilities.

Read more for details and contact information. Follow us on Twitter @lotwater!

Read More

Tuesday - June 3, 2014

Traffic Alert: DELAYED Night work on Carman Drive

Night work that was originally scheduled to begin on Carman Drive tonight, Tuesday, June 3 through June 16, has been delayed.

Other options for installing the 300 feet of storm drain pipe and manholes are currently being evaluated. More information will be provided once the revised schedule is determined.