Tuesday - December 30, 2014

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas. 

  • East Waluga parking lot pipeline disinfection
  • Highway 43 nighttime construction continues near Glenmorrie Drive
  • Chandler Road/ A Avenue – pipe installation expected to begin in mid-February

For the most up to date information on construction and road closures, follow @LOTwater on Twitter, visit work underway, call the hotline on 503-697-6502 or contact us.

Read More

Wednesday - December 17, 2014

Construction Tour Video

Take a drone’s-eye-view tour of the progress at the Lake Oswego Tigard Water Partnership’s facilities under construction. This unique view helps us gain a better perspective about the types of activities that are occurring at these vital sites that will eventually help deliver high-quality drinking water to the communities of Lake Oswego and Tigard for years to come.

Friday - December 12, 2014

West Linn Pipeline Construction Update

Highway 43 construction began this week in West Linn

Preliminary pipeline construction activities (saw-cutting asphalt and equipment mobilization) began on Monday, Dec. 8 at night on Highway 43 in West Linn near Mapleton Drive. On Sunday, Dec. 14, crews expect to begin nighttime pipe installation starting at the intersection of Mapleton Drive, working north along Highway 43 towards Lake Oswego. Schedules are subject to change.

Read More

Friday - December 5, 2014

Pipe installation under the Willamette River – a major milestone reached!

The Lake Oswego Tigard Water Partnership achieved a major project milestone this fall with the installation of a new 36-inch diameter waterline under the Willamette River. This monumental endeavor was accomplished with minimal impacts to riverbeds, water and wildlife.

This short video shares the story of this remarkable feat of engineering ingenuity.

Read More