Wednesday - April 29, 2015

Let’s Celebrate National Drinking Water Week – May 3-9

When you turn on your tap and clean, safe water comes out...

Do you ever stop to think about how it gets there and where it goes when you're finished with it? The Lake Oswego Tigard Water Partnership and the communities of Lake Oswego and Tigard are celebrating Drinking Water Week from May 3-9. We invite you to celebrate by taking time to learn more about your water and celebrating the progress that is being made on your new water system.

Construction of the new system is well over half way–more than seven of the ten miles of large diameter pipe have been installed, and, by mid-2016, most major facilities will be complete and operational.

Once work is complete, Lake Oswego and Tigard will have the most reliable water system in Oregon—designed to modern earthquake standards, and utilizing an advanced treatment process that will produce safer and better tasting water year-round— delivered to homes and businesses all for about a penny per gallon!

In Oregon, we often take our drinking water for granted, but it's a finite resource. Significant costs and energy are required to treat our drinking water, deliver it to our taps, and manage the wastewater that goes down the drain. Spend a moment this week thinking about the essential role that water plays in your daily life.

Our water in Lake Oswego and Tigard is of the highest quality - let’s celebrate it!

Friday - April 24, 2015

WTP reaches another milestone

Water Treatment Plant Construction Update

Work at the site is successfully transitioning to a new phase, as the eight new structures that have been constructed are progressing through their startup and commissioning stages. The yellow tower crane has been removed, and the red tower crane will remain in order to service the major work occurring in the center and west of the site.

Read More

Thursday - April 23, 2015

B Avenue construction moves into the business district

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas:

  • B Avenue construction - pipeline installation moves into the business district
  • McVey Avenue pipe bridge - surveying begins next week
  • Highway 43 nighttime construction - pipeline testing continues

For the most up to date information on construction and road closures, follow @LOTwater on Twitter, visit work underway, or contact us.

 

Read More

Tuesday - April 21, 2015

Crews begin tunneling under I-5 in Tigard

Tigard Pipeline and Bonita Pump Station Construction Update

This construction update includes all work in Tigard for the project.

Keep reading for specific information on each location:

  • Bonita Road Pipeline
  • Bonita Pump Station
  • Milton Court

Read More

Friday - April 17, 2015

Restoration of concrete panels continues on Highway 43

West Linn Pipeline Construction Update

This update includes construction work in the following areas. Read more for specific information on each topic:

  • Highway 43 - permanent trench patch complete; concrete panel work continues
  • Mapleton Drive - pipeline construction expected to begin soon
  • Neighborhood construction meetings - new meeting location and frequency
  • Meet the Mapleton Drive Pipeline Contractor - Meeting to be held May 19

 

Read More

Thursday - April 9, 2015

Pipeline construction down B Avenue moving swiftly along

Lake Oswego Pipeline Construction Update

This update includes construction work in the following areas:

  • B Avenue construction - pipeline installation is underway
  • Highway 43 nighttime construction - permanent trench patch complete
  • McVey Avenue pipe bridge - work expected to begin in May

For the most up to date information on construction and road closures, follow @LOTwater on Twitter, visit work underway, or contact us.

Read More

Friday - April 3, 2015

Night construction on Bonita Road begins next week

Tigard Pipeline and Bonita Pump Station Construction Update

These construction updates will now include all work in Tigard for the project.

Keep reading for specific information on each location:

  • Bonita Road Pipeline
  • Bonita Pump Station
  • Milton Court

Read More