Monday - August 31, 2015

New filters taking shape at the treatment plant

Water Treatment Plant Construction Update

Information about onsite work over the next few weeks includes:

Truck traffic route change reminder

While Mapleton Drive pipeline construction is underway, the WTP contractor will be using Kenthorpe Way to enter and exit the plant site. Neighbors on Kenthorpe Way should expect an increase in truck traffic during this time.

Read More

Friday - August 21, 2015

Bonita Pump Station taking final steps towards completion

Tigard Pipeline and Bonita Pump Station Construction Update

This construction update includes all work in Tigard for the project. Read more for specific information on each location:

  • Bonita Pump Station
  • Bonita Road Pipeline

Read More

Monday - August 17, 2015

Night work begins on McLoughlin Boulevard (Hwy. 99E)

Gladstone Pipeline and River Intake Construction Update

This update includes construction work in the following areas. Read more for specific information on each location:

  • River Intake Pump Station (RIPS) - demolition almost complete!
  • Nissan dealership, Teriyaki Grill and River Road - final pipeline crossing
  • McLoughlin Blvd. (Hwy. 99E) - night work begins tonight

Read More

Friday - August 14, 2015

Special Construction Reminder: Lake Oswego

Pipeline Work at Railroad Crossing on State Street Requires 48-Hour Weekend Construction Beginning Aug. 15

Beginning Saturday, Aug. 15 at 6 a.m., crews will start a period of 48-hour, continuous work to install the Lake Oswego Tigard Water Partnership’s new pipeline under the railroad tracks on State Street (Highway 43). Construction is expected to occur until as late as 6 a.m. on Monday, Aug. 17.

Travelers should expect significant delays and traffic congestion in downtown Lake Oswego during this 48-hour period. The Partnership encourages travelers to avoid the area, if possible, and use alternate routes.

Read More

Thursday - August 6, 2015

Pipeline Work at Railroad Crossing on State Street Requires 48-Hour Weekend Construction Beginning Aug. 15

In the news...

LAKE OSWEGO, Ore. – Beginning Saturday, Aug. 15 at 6 a.m., crews will start a period of 48-hour, continuous work to install the Lake Oswego Tigard Water Partnership’s new pipeline under the railroad tracks on State Street (Highway 43). Construction is expected to occur until as late as 6 a.m. on Monday, Aug. 17.

Read More

Wednesday - August 5, 2015

Questions about the Partnership’s water source and water rights?

The City of Lake Oswego holds two water rights on the Clackamas River, one issued in 1967 for 32.3 million gallons per day (mgd) and one issued in 1973 for 5.8 mgd. The total amount of water allowed to be used under these two permits is 38 million gallons per day (MGD).  Half of Lake Oswego’s larger 1967 water right (total of 16 mgd) is certificated—meaning it has completed the state permitting process and is considered a property right, which cannot be revoked. The other half is in the permit development process, along with the 5.8 mgd right.

Read More

Tuesday - August 4, 2015

Questions about the Partnership’s water source and water rights?

In the news...

The City of Lake Oswego holds two water rights on the Clackamas River, one issued in 1967 for 32.3 million gallons per day (mgd) and one issued in 1973 for 5.8 mgd. The total amount of water allowed to be used under these two permits is 38 million gallons per day (MGD).  Half of Lake Oswego’s larger 1967 water right (total of 16 mgd) is certificated—meaning it has completed the state permitting process and is considered a property right, which cannot be revoked. The other half is in the permit development process, along with the 5.8 mgd right.

Read More