Thursday - April 14, 2016

Site improvement preparations begin at the plant

Water Treatment Plant Construction Update

Miscellaneous piping work

Crews continue installing utility lines for the new administration building – located on the north side of the structure. Work involves excavating, placing pipe, and backfilling the trench. Starting April 14, crews will begin installing a sewer line on site which will connect to the main sewer line on Kenthorpe Way. During this work, there will be a single lane closure near the plant frontage on Kenthorpe Way, as crews connect the line. No parking will be permitted during work hours on the south side of Kenthorpe Way, between the two plant entrances. This is expected to be complete mid-next week. Neighbors close to the site on Kenthorpe Way should expect an increase in noise and vibration during these activities.

Read More

Tuesday - April 5, 2016

ADA ramp work begins on McVey Avenue and State Street

Lake Oswego Pipeline Construction Update

This update includes work in the following areas. Read more for specific information on each location:

  • McVey Avenue pipe bridge - new water pipeline now online!
  • McVey Avenue and State Street intersection - ADA ramps starting tomorrow

Read More