Thursday - January 30, 2014

Twin Fir Sewer Replacement

The sanitary sewer line along a portion of Twin Fir Road will be replaced during February 11- 25. During that time, the road will remain open but flaggers will guide traffic through the area.  The sewer line is being moved to make room for the Lake Oswego Tigard Water Partnership pipeline that will be installed in Twin Fir in May.

Work hours will be between 7 a.m. and 6 p.m. (daylight permitting) Monday through Friday.  Neighbors can expect to see an excavator, dump trucks hauling material out and in, a small roller for paving and pickups.  All materials and equipment will be removed at the end of the work day.  The trench will be temporarily patched when the project is completed and repaved with a more drivable surface a short time later. 

Thank you for your patience during this work.  We apologize for any inconvenience. For more information, please call 503-697-6502 or contact us.