River Intake Construction Update

Concrete pour earlier this week to 56-foot level

The 56-foot level concrete pour was completed this week, bringing the level of the river intake pump station to about the entryway height.

Over the next few weeks, crews will be installing interior forms and pouring concrete for the interior walls and the 56 foot level slab.

Neighbors may notice an increase in noise and truck traffic during concrete pours. Work hours are 7 a.m. to 6 p.m. Monday through Friday, with some work occurring on Saturdays as well.

We apologize for the inconvenience this work may cause and thank you for your patience as construction progresses.

Gladstone Pipeline Construction

A pipeline contractor has been hired for the installation of the pipeline through Gladstone. Look for an invitation to a “Meet the Contractor” meeting to be held sometime in June. This will be a good opportunity to learn about the work approach, anticipated schedule and have your questions answered.