Thursday - May 1, 2014

Waluga Reservoir 2 - Meet the Contractor Meeting and Construction Update

We hope that you can join us to meet representatives from Ward-Henshaw Construction and learn more about the Waluga Reservoir 2 construction, which will begin in mid May.

The Meet the Contractor meeting will be held on Wednesday, May 14 from 7 p.m. to
8:30 p.m. at the West End Building, Santiam Room, 4101 Kruse Way, Lake Oswego. We will have information about the project, the work schedule, and what to expect in the neighborhood.

Starting the week of May 12, expect to see some preconstruction activity on site at 4800 Carman Drive, including mobilizing equipment, removing tree stumps, and installing erosion control fencing. Work hours will be 7 a.m. to 6 p.m. Monday to Friday.

For more information, contact us or call the hotline at 503-697-6502.