Thursday - August 7, 2014

Waluga Reservoir 2 (WR2) Special Construction Update – Concrete Pour

Reservoir foundation rebar ready for the concrete pour on Friday

Tomorrow (Friday, August 8th), crews will be pouring concrete for half the reservoir foundation. Expect to see 15-20 dump trucks traveling to and from the site as well as a concrete pump truck. The truck traffic and pump truck will produce some noise. Flaggers will guide the trucks in and out of the site, so please approach the Carman curves cautiously. The work should take 4-6 hours.

Work hours are 7 a.m. – 6 p.m., Monday – Friday. We apologize for any inconvenience this work may cause and thank you for your patience during construction of this important water storage project.

For more information about the project, please contact-us via email, call the hotline at 503-697-6502, follow @lotwater on Twitter or visit the Lake Oswego page or the “all work underway” map at lotigardwater.org/