West Linn Pipeline Construction Update: Horizontal Directional Drilling site (end of Mapleton Dr.)

Loading 17" drill pipe for the pilot hole

The new steering tool (gyroscope) arrived earlier this week, and drilling of the pilot hole under the river resumed. A new, quieter generator for the solids separation tank was also installed this week. You can learn more about this process by reading Water Savvy Issue 9: Horizontal Directional Drilling

The pilot hole is about 50% complete! The hole is being drilled through rock and is currently being upsized from 12” to 17“ diameter. One or two more passes with larger drill bits will continue over the next four months until the hole is large enough for the pipe to be pulled through.

During drilling, neighbors may hear noise from the drill rig, solids tank generator and an increase in truck traffic. Work hours are 7 a.m. - 7 p.m. Monday through Friday, and Saturdays from 9 a.m. - 5 p.m.

Read more for information about the Neighborhood Construction Meeting.

Neighborhood Construction Meetings at the Burgerville in West Linn

The 22nd bi-monthly neighborhood construction update meeting was held on Tuesday, August 5, at Burgerville in West Linn. Meeting materials are posted on the project website on the “past public meetings” page. The August 5 summary, will be posted shortly.

The next neighborhood construction meeting will be held on August 19, at 6 p.m in the downstairs restaurant area at Burgerville, 18350 Willamette Drive in West Linn. Meetings are held at 7:30 a.m. on the first Tuesday of the month and 6 p.m. on the third Tuesday of the month. Meetings include updates on the HDD pipeline work and water treatment plant work occurring in West Linn.