West Linn Pipeline Construction Update: Horizontal Directional Drilling site (end of Mapleton Dr.)

The solids separation process separates material extracted during drilling. Gravel and rock is filtered and hauled off-site. Drilling fluid is recycled and reused during the HDD process.

A milestone was reached last week, with the successful completion of the pilot hole! Drilling has been ongoing for a few weeks from either side of the river, with both drills meeting in the middle to complete the pilot hole.

Crews have now started the process of upsizing the hole to 36”. More passes will be made with larger drill bits (or reamers) over the next few months until the hole is large enough for the pipe to be pulled through.

During drilling work, neighbors may hear noise from the drill rig and an increase in truck traffic. Work hours are 7 a.m. - 7 p.m. Monday through Friday, and Saturdays from 9 a.m. - 5 p.m. No work will occur over the Labor Day weekend, from Saturday, August 30 – Monday, September 1.

Neighborhood Construction Meetings at the Burgerville in West Linn

The 23rd bi-monthly neighborhood construction update meeting was held on Tuesday, August 19, at Burgerville in West Linn. Meeting materials are posted on the project website on the “past public meetings” page. The August 19 summary, will be posted shortly.

The next neighborhood construction meeting will be held on September 2, at 7:30 a.m. in the downstairs restaurant area at Burgerville, 18350 Willamette Drive in West Linn. Meetings are held at 7:30 a.m. on the first Tuesday of the month and 6 p.m. on the third Tuesday of the month. Meetings include updates on the pipeline work and water treatment plant work occurring in West Linn.

For more information, drop in to a bi-monthly meeting at Burgerville, visit the work underway map or contact us.