Friday - February 13, 2015

Waluga Reservoir coming together inside and out

Mixing manifold and pipe supports

Roof hatch

Waluga Reservoir 2 (WR2) Construction Update

Mixing manifold

Crews have removed the scaffolding and shoring inside the WR2 that were needed to support the roof and have hauled the materials off site. Over the next few weeks, they will install the reservoir’s mixing manifold and pipe supports.

WR2 wrapping and roof

The cable wrapping of WR2 is complete and the last of the shotcrete has been applied. Crews are now working on the roof to install the remaining roof hatches as well as the lightning proctection.

Pipe Vault

At the end of March, the pipe vault that connects the WR2 to Tigard’s water system will be poured, including floor and walls, structural steel will be installed, and, upon completion, painted.

Please note: For the safety of hikers and park visitors, the entrace to the Parkhill path will be closed over the next several weeks as crews excavate in the area in preparation for the new water pipeline.

Project information

For the most up to date information about the project, please visit work underway or contact us.