Architectural touches progress for the new WTP administration building

Siding and brick veneer being installed on the south and north side of the new administration building

Siding and brick veneer being installed on the south and north side of the new administration building

Concrete masonry blocks work on the walls of the pump room

Information about onsite work is outlined below. Please note, schedules are subject to change.

Truck traffic route reminder: with major pipeline construction on Mapleton Drive complete and the road open to through traffic, the WTP contractor will resume using Mapleton Drive to enter the WTP construction site, and Kenthorpe Way to exit the site.

Administration building – north of site

Architectural work is progressing on the administration building. Frames and windows are almost complete! Siding and brick veneer placement is underway, and will continue over the coming weeks. Inside the structure, sheet rock has been installed and painting is taking place.

Miscellaneous piping and site work

The electrical duct bank has been installed from the electrical building to the administration building. Crews will now begin installing a water line for the administration building – located on the north side of the structure. Work involves excavating, placing pipe, and backfilling the trench. Neighbors close to the site on Kenthorpe Way should expect an increase in noise and vibration during these activities.

This spring, curb and gutter improvements are expected to take place along both the Mapleton and Kenthorpe frontages of the site. This is in preparation for the street resurfacing that will be conducted by the City of West Linn this summer. Over the coming months, crews will begin placing new site walls and preparing some areas for hardscaping and landscaping improvements across the site.

Washwater recovery basin – northwest of site

Concrete masonry blocks are now in place for the walls of the pump room at the south end of the washwater basin (pictured left). Crews will soon begin installing the roof trusses, decking and weather barrier coatings. Neighbors should expect some intermittent metal-on-metal noise during the roof work.

New filters – northwest of site

The last major concrete pour for the filters is expected to take place next week! Mechanical and structural work continues in the filter gallery. Over the next week, crews will be backfilling the south side of the filters – located in the center of the site. Neighbors may notice an increase in vibration during this activity.

Finished water pump station and clearwell – south of site

Startup and testing of the clearwell, surge tank and finished water pump station is underway and continues over the next month.

Neighborhood construction meetings – new frequency

Meetings are now held once a month at the Robinwood Station, 3706 Cedaroak Drive, West Linn, on the third Tuesday of the month at 6 p.m. The next neighborhood construction meeting will be held on Tuesday, March 15 at 6 p.m. Please attend to stay up-to-date on construction progress in West Linn and ask the project team questions.

Work hours

Work hours are 7 a.m. to 7 p.m., Monday to Friday, and 9 a.m. to 5 p.m. on Saturday.

WTP construction tours

The next tour will be held on Thursday, March 24 at 10 a.m. Tours are held every two months on the fourth Thursday. Advance registration is required and space is limited. Please contact us and indicate in the subject line you would like to attend the next tour, along with your contact information.

Site plan and glossary

Please refer to the site plan for locations of each structure or our glossary of terms for construction and operation of the WTP.

For more information about the project, please contact usYou can also drop-in to a neighborhood construction meeting, call (503) 697-6502 or follow @lotwater on Twitter.