Tuesday - April 5, 2016

ADA ramp work begins on McVey Avenue and State Street

Lake Oswego Pipeline Construction Update

This update includes work in the following areas. Read more for specific information on each location:

  • McVey Avenue pipe bridge - new water pipeline now online!
  • McVey Avenue and State Street intersection - ADA ramps starting tomorrow

McVey Avenue pipe bridge - new water pipeline now online!

Last week, crews successfully completed disinfecting the pipeline and placed it into service. The newly installed finished water pipeline is now providing water from the water treatment plant in West Linn to the Waluga Reservoir in Lake Oswego!

Over the next few weeks, miscellaneous cleanup work will be taking place at the bridge, and crews will be slowly demobilizing equipment.

McVey Avenue and State Street intersection - ADA ramps starting tomorrow

Starting tomorrow, Wednesday, April 6, through Friday, April 8, crews will begin preparing and pouring the ADA ramps along the northbound lane of State Street near George Rogers Park and Green Street. Work hours on State Street are 9 a.m. - 3 p.m., with lane closures in place near the park.

This Thursday, April 7 and Friday, April 8, crews will be preparing and pouring ramps near the southbound turn lane onto McVey Avenue, at State Street. To minimize traffic impacts, this work will be conducted at night from 8 p.m. - 5 a.m.

Starting Monday, April 11 through Friday, April 15, work will take place on the McVey Avenue ADA ramps between State Street and the Bay Roc Apartment Complex. This will likely be conducted during the day, from 9 a.m. – 7 p.m., with some lane closures in place. Please watch for traffic control devices and stay alert. During this work, there will be no parking along the south side of McVey Avenue, near the Bay Roc Apartment Complex.

Once the ADA ramps are complete, paving will be scheduled, however, this is also weather dependent.

For more information about the project, please contact us or follow @lotwater on Twitter.