Hardscaping improvements continue at the water plant

An ozone generator uses electrical energy to produce ozone from oxygen for the water treatment process.

Forming curbs and sidewalk in front of the new administration building.

Water Treatment Plant Construction Update

Information about onsite work is outlined below. Please note, schedules are subject to change.

Ozone system - northeast of site

Work continues to progress on the new ozone system. New equipment is being installed inside the structures. The contractor and water treatment plant staff are preparing to begin testing and commissioning the new state-of-the-art ozone system, which will be online in the coming months.

Architectural siding and pearl panels are being placed on the exterior of the ozone generator building. The brick veneer is complete. Frames and glass are being installed for the windows.

Miscellaneous duct bank and piping work continues around the new ozone structures and administration building. During these activities, neighbors close to the site should expect some noise and vibration during work hours.

Site improvements and hardscaping

Hardscaping and site improvements are ongoing across the site. Site improvements include stone walls, sidewalks, catch basins, curbs, site walls and hardscaping work. These activities involve digging and preparing the site, placement of materials, forming, compacting, pouring concrete and saw-cutting stone. During this work, neighbors close to the site should expect an increase in intermittent noise and vibration from equipment.

Crews have been clearing out the temporary storage shed located in the southwest corner of the site. In the next few weeks, the shed will be removed. Neighbors close to the site should expect an increase in noise and possible vibration during the removal of the shed.

Neighborhood construction meetings – next meeting February 21

Meetings are held once a month at the Robinwood Station, 3706 Cedaroak Drive, West Linn, on the third Tuesday of the month at 6 p.m. The next neighborhood construction meeting will be held on Tuesday, February 21 at 6 p.m. Please attend to stay up-to-date on construction progress in West Linn and ask the project team questions.

Completion date

Construction at the plant is expected to be complete in late spring 2017 – this includes all landscaping and site work. The pedestrian pathway, linking Mapleton Drive to Kenthorpe Way, will be opened after construction is complete.

Work hours

Work hours are 7 a.m. to 7 p.m., Monday to Friday, and 9 a.m. to 5 p.m. on Saturday.

WTP tours

The next tour will be held on Thursday, March 23 at 10 a.m. Tours are typically held every two months on the fourth Thursday. Advanced registration is required and space is limited. Please contact us and indicate in the subject line you would like to attend the next tour, along with your contact information.

Site plan and glossary

Please refer to the site plan for locations of each structure or our glossary of terms for construction and operation of the WTP.

For more information, please contact us or attend a neighborhood construction meeting.